As the Easter weekend rolls in, our hardworking teams are taking a well-deserved break — except for our curing teams, who continue to ensure that the concrete sets perfectly, keeping the momentum alive.
We’re thrilled to share that we successfully cast the fourth floor slab of Block B on the 16th of April 2025, and we’re gearing up to cast the fourth floor slab of Block A by the 24th of April 2025.
Steady progress, strong foundations, and exciting times ahead — we can’t wait to soon introduce Eternity Heights to the market.
The dream is steadily taking shape!